Spiral welded steel pipe production technology: based on strip steel coil plate for raw materials, through extrusion, with automatic double wire welding double-sided submerged arc welding technology with the spiral seam pipe. Spiral steel pipe for steel structure material classification: 16 mn material spiral steel pipe, Q345B spiral steel pipe, L245 spiral steel pipe, L360 spiral steel pipe, X40 - X80 spiral steel pipe. Commonly used standards of the spiral steel pipe can be divided into: the SY/T5037-2008 (solid, also known as the common fluid conveying pipe with spiral seam submerged arc welding steel pipe), GB/T9711.1-2008 (national standard, also known as oil and gas industry conveying pipe delivery technical conditions in the first part: grade A steel pipe (demanding with GB/T9711.2 grade B steel pipe)), API 5 l (American petroleum institute, also known as the pipeline steel pipe; which can be divided into PSL1 and PSL2 two levels), SY/T5040-2008 (with spiral weld steel pipe pile).
Spiral structural steel pipe in strip steel coil plate for raw materials, often warm extrusion molding, with automatic double wire welding double-sided submerged arc welding technology with the spiral seam pipe.
(1) the raw material is steel strip coil, wire, flux. Have to pass strict physical and chemical inspection before investment.
(2) the strip head to tail docking, use single or double wire submerged arc welding, after rolled DSAW steel pipe adopts automatic submerged arc welding repair welding.
(3) before shaping, strip after flattening, cutting edge, edge planing, transmission and cleaning the surface to the flanging process.
(4) on both sides of the electric contact pressure gauge control conveyor under the pressure of oil cylinder pressure, ensure the smooth delivery of strip steel.
(5) the use of external control or internal control roll forming.
(6) the weld gap control device to ensure that meet the requirements of welding seam clearance, pipe diameter, and quantity of the wrong side of weld gap are tightly controlled.
(7) welding and welding are used within the United States Lincoln welding machine for single or double wire submerged arc welding, to obtain the stable welding specification.
(8) after welding the weld passes the online continuous ultrasonic automatic meter check, ensure the spiral weld nondestructive testing coverage of 100%. If there are defects, automatic alarm and spray tags, production workers to adjust process parameters, in a timely manner to eliminate defects.
(9) by air plasma cutting machine to cut the steel tube into single.
After cut into single pole (10), the head of every batch of steel pipe should be strictly check system, check the weld mechanical properties, chemical composition, amalgamation, steel tube surface quality and the nondestructive flaw detection, ensure that qualified pipe process, can be formally put into production.
(11) have continuous acoustic detection of weld mark parts, after manual ultrasonic and X-ray check, if there are defects, after repair, again through the nondestructive inspection, until defects have been eliminated.
(12) strip steel butt weld and fellowship with spiral weld d joint in the tube, all pass X-ray films and television inspection. (13) each steel pipe after hydrostatic pressure test, radial sealing for the pressure. Test pressure and time are controlled strictly by mild steel pipe hydraulic microcomputer testing device. The parameters automatically printed out.
(14) pipe end machining, make the end verticality, slope Angle and the blunt edge to get accurate control.